Daily Field Report
Date :09/17/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/17/2024 08:00
Onsite Hours :9:00
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :Cludy
Departure Time :09/17/2024 17:00
ASEC Technician Name :Solomon Cherie
Observations/Finding
Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:
Backfilling of the storm line BH2 to BH3 and sewer lines 1.8 to 3.0 continued today.
Compaction was not completed today so no testing was performed.
Please contact us if you have any questions regarding this report or the density test results for today.

Storm line BH2- BH3

Sewer line 1.8-3.0
Technician Signature / DateSolomon Cherie, September 17, 2024
Reviewer Name / DateKenneth Mosman, February 02, 2025