Density Test Report

Date :11/27/2024
Project No :2024C202
Client Company :CCG
Arrival Time :11/27/2024
Onsite Hours :
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Sunny
Departure Time :
ASEC Technician Name :Solomon Cherie

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
11/27/2024 119 29.9 85.5 S-02 97.2 24.9 88.0 95 D6938 Fail
Location : Lot#114, Elv/Depth :-6.0'
Comment : Gauge Serial No. :30942
Technician Signature / DateSolomon Cherie, November 27, 2024
Reviewer Name / DateKenneth Mosman, January 10, 2025