Daily Field Report

Date :01/27/2025
Project No :2024C202
Client Company :CCG
Arrival Time :01/27/2025 07:30
Onsite Hours :01:30
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Cloudy and drizzle
Departure Time :01/27/2025 09:00
ASEC Technician Name :

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Upon arrival, our representative found the site to be muddy and wet overall with an additional 1 inch of rain falling later.  After consultation with the contractor, it was decided that grading operations would be terminated for the day.

Please contact us if you have any questions regarding this report.

 

 

 

Picture depicting muddy with patches of water

Technician Signature / DateSolomon Cherie, January 27, 2025
Reviewer Name / DateKenneth Mosman, February 01, 2025