Daily Field Report

Date :01/25/2025
Project No :2024C315
Client Company :J. Chapman Const.
Arrival Time :01/25/2025 09:00
Onsite Hours :04:00
Name of the Project :Cottages at Villa Rica - Rock Blasting
Project Location :Villa Rica
Weather :cold
Departure Time :01/25/2025 13:00
ASEC Technician Name :Mahendra Mylabathula

Observations/Finding

The aforementioned AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The contractor performing the work was Precision Blasting. The following observations were made on-site:

Drilling Data:

The drilling operation began at Lateral 124, located north of Lot 124 and south of Lot 45. During the drilling process, rock formations were encountered at a depth of approximately 13 feet in 13 out of the 15 holes. Drilling in this area was conducted in three rows, with rows spaced approximately 6 feet apart and drilling locations spaced 8 feet apart within each row.

Each hole was carefully inspected after drilling to ensure the correct depth was achieved. However, after completing 14 holes, an issue arose with the drilling equipment: the drill rig was unable to extract the drill steel from one of the holes. As a result, the team decided to halt operations to address the equipment malfunction.

A layout drawing showing the approximate area where drilling was performed on this day is attached to this report.

We appreciate the opportunity to assist you with this project. If you have any questions regarding this report, please feel free to contact us. We would be happy to discuss it with you.

Technician Signature / DateMahendra Mylabathula, January 25, 2025
Reviewer Name / DateRamchandra Mogulla, January 28, 2025