Daily Field Report

Date :01/27/2025
Project No :2024C202
Client Company :CCG
Arrival Time :01/27/2025 08:00
Onsite Hours :01:00
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Cloudy and drizzle
Departure Time :01/27/2025 09:00
ASEC Technician Name :Solomon Cherie

Observations/Finding

The site is muddy with patches of water. The rainfall recorded is one inch. I discussed the situation with the superintendent that it is to wet to do backfill. The superintendent finally decided to shut down the work for the day.

Picture depicting muddy and too wet soil

Technician Signature / DateSolomon Cherie, January 27, 2025
Reviewer Name / DateKenneth Mosman, February 01, 2025