Daily Field Report

Date :01/31/2025
Project No :2024C202
Client Company :CCG
Arrival Time :01/31/2025 08:00
Onsite Hours :04:00
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Cloudy and drizzle
Departure Time :01/31/2025 12:00
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Observed the placement of fill/grading for Lots #31 and the back of Lots #26 through 30 today, spread by a 61Pxi Komatsu Bulldozer and compacted using a 815F CAT. This area had previously been the site for a temporary pond.  Cutting continued from the adjacent roadway using a 349E CAT Excavator and hauling with two 745C dump trucks.  Compaction tests were performed using a nuclear density gauge.  General probing and proof-rolling were also performed to verify stability.

Overall, the results of density testing confirmed that fill compaction met the project and ASTM requirements. Results are attached in a separate report.

Please contact us if you have any questions regarding this report or of the density test results.

 

Picture showing thin strip of backfill behind busing pads 26-30

Picture depicting lot #31 at subgrade

Technician Signature / DateSolomon Cherie, January 31, 2025
Reviewer Name / DateKenneth Mosman, February 01, 2025