Daily Field Report

Date :02/14/2025
Project No :2024C202
Client Company :CCG
Arrival Time :02/14/2025 08:00
Onsite Hours :01:00
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Sunny
Departure Time :02/14/2025 09:00
ASEC Technician Name :Solomon Cherie

Observations/Finding

At the request of the client, AS Engineering and Consulting (ASEC) visited the site to observe construction material testing and earthwork activities. However, due to the current site conditions, no work was performed.

  • The site was extremely muddy with standing water and ice sheets throughout the area.
  • Due to these conditions, it was impossible to perform any dirt work or compaction activities.
  • The contractor did not perform any work on-site during this visit.
  • The recommendation is to allow time for the site to dry before resuming earthwork operations.

Recommendations:

  • Site conditions should be reassessed before scheduling further earthwork activities.
  • Additional drying time may be necessary before proceeding with any soil placement or compaction.

We appreciate the opportunity to assist with this project. Should you have any questions regarding this report, please do not hesitate to contact us.

Picture showing thin layer of I e sheet

Picture depicting muddy and wet surface

Technician Signature / DateSolomon Cherie, February 14, 2025
Reviewer Name / DateRamchandra Mogulla, February 14, 2025