Daily Field Report

Date :02/18/2025
Project No :2024C315
Client Company :J. Chapman Const.
Arrival Time :02/18/2025 09:30
Onsite Hours :06:00
Name of the Project :Cottages at Villa Rica - Rock Blasting
Project Location :Villa Rica
Weather :Sunny
Departure Time :02/18/2025 15:30
ASEC Technician Name :Micah Aycock

Observations/Finding

The aforementioned AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The contractor performing the work was Precision Blasting. The following observations were made on-site:

Drilling data:

Precision Blasting continued drilling operations today in the same pattern that they have been working on. This pattern included a trench in the middle and a mass rock pattern on either side of the trench. The area was between lot #187 and lot #59. These efforts are a continuation of precision blasting’s efforts to break up the large mass rock section in the northeast corner of the Cottages at Villa-Rica. Everything went according to plan and all drilling met with the production standards.

We appreciate the opportunity to assist you with this project. Should you have any questions regarding this report, please do not hesitate to contact us. We would be happy to discuss it with you.

Technician Signature / DateMicah Aycock, February 18, 2025
Reviewer Name / DateRamchandra Mogulla, February 26, 2025