Skip to content

Daily Field Report

Date :02/26/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :02/26/2025 08:00
Onsite Hours :08:00
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :sunny
Departure Time :02/26/2025 16:00
ASEC Technician Name :Vamsi Polisetty

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Seven Hills: Amenities

  • Upon arrival, the contractor was engaged in grading the roadway using a Komatsu PC 360LC. From the earlier days rain, aeration was performed by dozing/discing with a Komatsu 39px followed by compaction using a CAT563E.
  • The next lift of fill was started on the tennis court & parking area.

Nature walk: Artisan Built Housing

  • Savanna Excavation Report: The contractor resumed work adjacent to Lot #995, continuing from the previous day. Efforts were focused on addressing the rock encountered in the trench, utilizing the Kobelco SK 350LC excavator. Compaction efforts are being executed with a Hamm Shep Toe compactor and a remote-controlled compactor. By the end of the workday, the contractor successfully completed the manhole installation and began the backfilling process. Rock boulders and organic materials were observed at the job site. For further reference, pictures have been attached.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateVamsi Polisetty, February 26, 2025
Reviewer Name / DateKenneth Mosman, March 09, 2025