Daily Field Report

Date :03/05/2025
Project No :2024C315
Client Company :J. Chapman Const.
Arrival Time :03/05/2025 09:00
Onsite Hours :06:30
Name of the Project :Cottages at Villa Rica - Rock Blasting
Project Location :Villa Rica
Weather :Cloudy
Departure Time :03/05/2025 15:30
ASEC Technician Name :Micah Aycock

Observations/Finding

Site Visit Report – Cottages at Villa Rica

An AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The contractor performing the work was Precision Blasting.

Blasting Data:

Blasting operations took place today in the northwest corner, south of Manhole A1. A total of five laterals between Lot #40 and Lot #37 were blasted in a trench pattern. The total blasted area for all trench laterals was 912 square feet, with a calculated trench rock volume of 323.59 cubic yards. The average drilled hole depth was 9.58 feet.

These efforts are part of Precision Blasting’s ongoing work to break up the trench rock section in the northwest corner of the development. All drilling and blasting proceeded according to plan and met production standards.

We appreciate the opportunity to assist with this project. Please feel free to reach out if you have any questions or require further details.

Technician Signature / DateMicah Aycock, March 5, 2025
Reviewer Name / DateRamchandra Mogulla, March 14, 2025