Daily Field Report

Date :03/11/2025
Project No :2024C202
Client Company :CCG
Arrival Time :03/11/2025 08:00
Onsite Hours :01:30
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Clear sky
Departure Time :03/11/2025 09:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes and material submittals.  The following observations were observed on the site this day.

Upon arrival, the project site was observed to be too wet and muddy due to the one-inch rainfall from yesterday.

After conversation with the superintendent, he decided not to perform any backfilling, and elected to move topsoil.

Picture depicting patches of water

Technician Signature / DateSolomon Cherie, March 11, 2025
Reviewer Name / DateKenneth Mosman, April 29, 2025