Daily Field Report

Date :03/06/2025
Project No :2024C315
Client Company :J. Chapman Const.
Arrival Time :03/06/2025 10:00
Onsite Hours :06:00
Name of the Project :Cottages at Villa Rica - Rock Blasting
Project Location :Villa Rica
Weather :Sunny
Departure Time :03/06/2025 16:00
ASEC Technician Name :Micah Aycock

Observations/Finding

Site Visit Report – Cottages at Villa Rica

An AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The contractor performing the work was Precision Blasting.

Drilling Data:

Today’s drilling operations continued in the northeast corner of the development, between Lot #53 and Lot #54. The drilling followed a mass rock pattern with hole spacing of 6 feet.

We appreciate the opportunity to assist with this project. If you have any questions regarding this report, please do not hesitate to contact us. We would be happy to discuss any details further

Lot #53

Technician Signature / DateMicah Aycock, March 6, 2025
Reviewer Name / DateRamchandra Mogulla, March 14, 2025