Daily Field Report
Date :03/05/2025
Project No :2023C159
Client Company :CW Matthews
Arrival Time :03/05/2025 6:30
Onsite Hours :12:00
Name of the Project :Airfield Repairs 2021-23
Project Location :HJAIA, Atlanta, GA
Weather :cloudy
Departure Time :03/05/2025 18:30
ASEC Technician Name :Aminullah Azimi
Observations/Finding
Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:
Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- Observations:
- Visual verification of compliance with project drawings, specifications, and codes.
- Placement and testing of concrete for Concourse D.
- Inspection of under-drainage for Romeu 2 and Romeu 3.
- Findings:
- A cracked pipe was identified in the under-drainage system.
- The contractor may need to replace or repair the pipe to address this issue
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.








Technician Signature / DateAminullah Azimi, March 5, 2025
Reviewer Name / DateKenneth Mosman, April 29, 2025