Daily Field Report

Date :03/14/2025
Project No :2024C315
Client Company :J. Chapman Const.
Arrival Time :03/14/2025 10:00
Onsite Hours :07:00
Name of the Project :Cottages at Villa Rica - Rock Blasting
Project Location :Villa Rica
Weather :Sunny
Departure Time :03/14/2025 17:00
ASEC Technician Name :Micah Aycock

Observations/Finding

The AS Engineering and Consulting (ASEC) representative visited the Cottages at Villa Rica site to monitor drilling and rock removal operations. The contractor performing the work was Precision Blasting. The following observations were made on-site:

Drilling Data:

Today’s drilling operations took place in the northeast corner of the development. The drilling was in-between lot #51 and lot #52. The pattern that was drilled was mass rock and had hole spacing of 6×6. These efforts are part of Precision Blasting’s ongoing work to break up the small trench rock section in the northwest corner of the Cottages at Villa Rica. We appreciate the opportunity to assist with this project. Should you have any questions regarding this report, please do not hesitate to contact us. We would be happy to discuss any details further.

Technician Signature / DateMicah Aycock, March 14, 2025
Reviewer Name / DateKenneth Mosman, April 29, 2025