- Home
- Daily Field Report Report ID: 78983
- Edit Download Report
Daily Field Report
Observations/Finding
Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:
Observed the placement of fill/grading for Lots #62 and #63 today, spread by a 61Pxi Komatsu Bulldozer and compacted using a 815F CAT. Cutting continued from the adjacent roadway using a 349E CAT Excavator and hauling with two 745C dump trucks. Compaction tests were performed using a nuclear density gauge. General probing and proof-rolling were also performed to verify stability.
Overall, the results of density testing confirmed that fill compaction met the project and ASTM requirements. Results are attached in a separate report.
Please contact us if you have any questions regarding this report or of the density test results.

Picture depictimg Lot#112 backfilled to subgrade
