Skip to content

Daily Field Report

Date :04/03/2025
Project No :2025C146
Client Company :Davidson Homes, LLC
Arrival Time :04/03/2025 9:30
Onsite Hours :05:30
Name of the Project :Greene Farms Subdivision
Project Location :1451 Highway 113, Cartersville, Georgia
Weather :sunny
Departure Time :04/03/2025 15:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, a representative from AS Engineering and Consulting (ASEC) visited the project site to perform quality control inspection and testing services. Visual observation techniques were utilized to verify compliance with project drawings, specifications, applicable codes, and approved material submittals.

Observations:

During the visit, it was observed that the contractor was in the process of removing approximately 2.5 feet of topsoil. This exceeded the anticipated removal depth. The contractor was notified of the discrepancy and was advised to limit topsoil removal to a depth between 10 inches and 12 inches, in accordance with project requirements.

We appreciate the opportunity to provide services on this project. Should you have any questions or need further clarification regarding this report, please do not hesitate to contact us. We would be pleased to assist you.

Technician Signature / DateAminullah Azimi, April 3, 2025