Density Test Report

Date :04/18/2025
Project No :2025C150
Client Company :Davidson Homes
Arrival Time :04/18/2025
Onsite Hours :
Name of the Project :Riverwood Retaining Wall
Project Location :Dallas
Weather :sunny
Departure Time :04/18/2025
ASEC Technician Name :Russell Hendrix

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/18/2025 1 14.9 93.3 2025-021 SP 97.2 18.6 96.0 95 D6938 Pass
Location : Retaining wall North to South, Elv/Depth :6th lift
Comment : Gauge Serial No. :29588
04/18/2025 2 13.3 98.1 2025-015 SP 102.8 18.1 95.4 95 D6938 Pass
Location : North to South, Elv/Depth :6th lift
Comment : Gauge Serial No. :29588
04/18/2025 3 17.0 105.0 2025-009 SP 89.2 25.2 100.6 95 D6938 Pass
Location : North to South, Elv/Depth :6th lift
Comment : Gauge Serial No. :29588
04/18/2025 4 16.8 105.0 2025-009 SP 89.2 25.2 100.8 95 D6938 Pass
Location : North to South, Elv/Depth :6th lift
Comment : Gauge Serial No. :29588
04/18/2025 5 14.8 99.0 2025-015 SP 102.8 18.1 96.3 95 D6938 Pass
Location : North to South, Elv/Depth :6th lift
Comment : Gauge Serial No. :29588
Technician Signature / DateRussell Hendrix, April 18, 2025
Reviewer Name / DateKenneth Mosman, May 03, 2025