- Density Test Report Report ID: 80269
- This project is inactive from admin. Download Report
Density Test Report
Date :04/10/2025
Project No :2024C213
Client Company :WDG
Arrival Time :04/10/2025 9:00
Onsite Hours :9:00
Name of the Project :Covington Town Center PH II
Project Location :Covington, GA
Weather :sunny
Departure Time :04/10/2025 18:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 04/10/2025 | 1 | 18.5 | 103.6 | ASECP001 | 106.0 | 18.2 | 97.7 | 95 | D6938 | Pass |
| Location : | water storm trench, between MHB1 and MHB2, Elv/Depth :3 feet below finished grade | |||||||||
| Comment : | Gauge Serial No. :85759 | |||||||||
| 04/10/2025 | 2 | 19.2 | 104.4 | ASECP001 | 106.0 | 18.2 | 98.5 | 95 | D6938 | Pass |
| Location : | water storm trench, 22 feet west from MHB2, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | Gauge Serial No. :85759 | |||||||||
| 04/10/2025 | 3 | 20 | 105.6 | ASECP001 | 106.0 | 18.2 | 99.6 | 95 | D6938 | Pass |
| Location : | sewer trench, 31 feet west from existing MH , Elv/Depth :7 feet below finished grade | |||||||||
| Comment : | Gauge Serial No. :85759 | |||||||||
Technician Signature / DateAminullah Azimi, April 10, 2025
Reviewer Name / DateKenneth Mosman, May 02, 2025