Daily Field Report
Date :05/03/2025
Project No :2024C314
Client Company :Manhatten Const.
Arrival Time :05/03/2025 8:00
Onsite Hours :04:00
Name of the Project :Concourse B Grease Receptors
Project Location :HJAIA
Weather :rainy
Departure Time :05/03/2025 12:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:
-
Concrete Beam Transfer:
Concrete beam specimens were transported to our laboratory for compressive strength testing, adhering to ASTM C31/C31M standards for handling and curing. The beams remained in their molds during transport to prevent damage and moisture loss. -
Mold Stripping and Return:
After the required curing period, the concrete beams were stripped from their molds at our laboratory. The empty molds were subsequently returned to the CWM Laboratory for cleaning and preparation for future use.
Technician Signature / DateAminullah Azimi, May 3, 2025
Reviewer Name / DateKenneth Mosman, May 07, 2025