Density Test Report

Date :05/16/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :05/16/2025 07:45
Onsite Hours :03:15
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :sunny
Departure Time :05/16/2025 11:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
05/16/2025 1 25.5 0.0 2025-011 SP 115.0 15.5 0.0 98 D2937 Fail
Location : Lot #112, Elv/Depth :at finished grade
Comment : Moisture content check
05/16/2025 2 23.9 0.0 2025-011 SP 115.0 15.5 0.0 98 D2937 Fail
Location : Lot #33, Elv/Depth :at finished grade
Comment : Moisture content check
Technician Signature / DateSean Willett, May 16, 2025
Reviewer Name / DateKenneth Mosman, June 23, 2025