Skip to content

Daily Field Report

Date :06/02/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :06/02/2025 8:00
Onsite Hours :07:00
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :cloudy
Departure Time :06/02/2025 15:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, a representative from AS Engineering and Consulting (ASEC) visited the site to conduct quality control inspections and testing services. Visual observation techniques were employed to verify compliance with project drawings, specifications, applicable codes, and approved material submittals.

Observations from the Site Visit:

  1. Earthwork Activities: Work was in progress in the following areas:
    • Storm trench between MHC5 and MHC6.
    • Water line at the entrance.

Upon arrival, our representative observed active work on-site. However, the contractor did not bench back the trench or provide an iron safety box. As a result, the county inspector halted work for the day. Consequently, fill placement was not performed, and testing was not performed.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, June 2, 2025
Reviewer Name / DateKenneth Mosman, July 17, 2025