Daily Field Report

Date :06/04/2025
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :06/04/2025 8:00
Onsite Hours :9:00
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :cloudy
Departure Time :06/04/2025 17:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, a representative from AS Engineering and Consulting (ASEC) visited the site to provide quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings, specifications, applicable codes, and material submittals. The following observations were made on-site today:

  • The placement and compaction of backfill for the outlet control structures in pond-1 and pond 2 continued.
  • Upon arrival, our representative observed that pipe placement was in progress, with six-inch lifts being placed and compacted using jumping and trench compaction equipment. Compaction testing was performed along with general probing using a 3/8-inch diameter probe rod.

We appreciate the opportunity to serve you on this project. If you have any questions regarding this report, please feel free to contact us—we would be happy to discuss it with you.

Technician Signature / DateAminullah Azimi, June 4, 2025
Reviewer Name / DateKenneth Mosman, August 04, 2025