Density Test Report
Date :06/27/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :06/27/2025 08:30
Onsite Hours :
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :06/27/2025
ASEC Technician Name :Sean Willett
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 06/27/2025 | 3 | 15.9 | 89.3 | 0 | Infinity | D2937 | Pass | |||
| Location : | Roadway east side trash pit by Lot #90, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | Conducted 3point field Proctor: Dry density of 97.9 pcf @ 20.7% showing approx 91-92% compaction | |||||||||
| 06/27/2025 | 4 | 23.1 | 89.1 | 0 | Infinity | D2937 | Pass | |||
| Location : | West road way cut by lot 3 -5 , Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | Conducted 3point field Proctor : Dry Density of 97.9 @ 20.7% showing approx 91-92% compaction | |||||||||
Technician Signature / DateSean Willett, June 27, 2025
Reviewer Name / DateKenneth Mosman, August 06, 2025