- Home
- Daily Field Report Report ID: 82742
- Edit Download Report
Daily Field Report
Observations/Finding
As requested, a representative of AS Engineering & Consulting (ASEC) conducted a site visit to perform quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes, and approved material submittals.
2. Earthwork Activities
-
Placement and compaction of backfill materials were in progress in the following locations:
-
Water line trench at the entrance/pit area.
-
Backfill behind Retaining Wall #1.
-
-
During the observation, active placement of fill material was observed being performed in 1-foot lifts. Compaction was executed using a 12-ton sheeps-foot roller and trench compactors.
3. Compaction Testing
-
Compaction testing was carried out using a Troxler nuclear density gauge in accordance with ASTM D6938.
-
Additional verification was conducted with general probing, using a 3/8-inch diameter probe rod.
Test Results:
-
Water Line Trench:
-
Did not achieve the specified minimum 95% relative compaction based on maximum dry density (MDD) per the Standard Proctor method (ASTM D698).
-
Moisture content exceeded the specified permissible range, indicating the soil was overly wet.
-
-
Retaining Wall #1 Backfill:
-
Achieved the specified minimum 95% relative compaction per ASTM D698.
- Our ASEC representative arrived on site to observe the placement of MSE retaining walls #1.It was noted that behind the block and in the cells, No. 57 stone was used.
Every 2nd course a geotextile fabric was placed followed by an 8-inch compacted lift.
No. 57 stone was utilized 1-foot behind the block and within the cells.
No remedial recommendation was made.
-
Notes:
-
Moisture content was above the specified range. Under this condition, soils require scarification and aeration (moisture correction) prior to re-compaction. The contractor was notified but did not implement corrective action. Consequently, the trench was backfilled without achieving the required compaction.
4. Recommendations & Required Remediation
-
Undercut and Remove Non-Conforming Material
Excavate the inadequately compacted zones around the water line to a depth sufficient to remove all non-conforming soils. -
Moisture Conditioning
Adjust the moisture content of the excavated soil to within ±2% of the laboratory-determined Optimum Moisture Content (OMC) before re-compaction
Thank you for the opportunity to support this project. Should you have any questions or wish to discuss these findings further, please feel free to contact us.













