Daily Field Report
Observations/Finding
As requested, a representative from AS Engineering and Consulting (ASEC) visited the site to perform quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes, and approved material submittals. The following observations were made during the site visit:
Our representative observed a proof-roll and performed density testing on roadway this day.
A proof-roll was performed on the roadway before starting fill placement at 6 feet below finished grade in the front of Lot #80 and Lot #81 using a fully loaded tandem-axled dump truck. Multiple passes were made across the area. No significant yielding or deflection was observed during the proof-roll. One small approximate (18’x18′) area was recommended to be undercut 2 feet and replace with suitable fill.
We appreciate the opportunity to support your project. If you have any questions regarding this report, please do not hesitate to contact us. We are happy to discuss our findings in greater detail.