Daily Field Report

Date :07/03/2025
Project No :2025C160
Client Company :Artisan
Arrival Time :07/03/2025 08:00
Onsite Hours :07:30
Name of the Project :Rockmart Township - 115 Felton Drive
Project Location :Rockmart
Weather :Sunny
Departure Time :07/03/2025 15:30
ASEC Technician Name :Austin Coleman

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Our representative found that the soils from the roadways around the west side of the project matched the field proctor that had been performed on the jobsite previously and that the roadways were compacted to job specifications based on the field proctor. A proof-roll was performed for the lower lots of the east side of the project and found that the fill placed was found to be stable under a loaded tandem-axled dump truck.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAustin Coleman, July 3, 2025
Reviewer Name / DateKenneth Mosman, August 07, 2025