Skip to content

Daily Field Report

Date :07/15/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :07/15/2025 09:00
Onsite Hours :06:30
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :Sunny
Departure Time :07/15/2025 15:30
ASEC Technician Name :Safiullah Momand

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the mentioned date, the following activities were in progress at the project site:

  1. Placement of the first layer of Graded Aggregate Base (GAB) with an 8-inch thickness over the subgrade for the west deceleration lane.

  2. Excavation work for the access road to the project site.

  3. Installation of the stormwater inlet for the access road.

Observations by the Writer:

  1. The subgrade at the deceleration lane displayed soft materials at two specific locations.

  2. The backfill around the stormwater inlet appeared not to be adequately compacted.

Recommendations by the Writer:

a. Excavate and remove the soft material at the identified points of the deceleration lane up to a depth of 8 inches, then replace with compacted GAB material. This problem was resolved by the contractor while on site.

b. Properly compact the backfill surrounding the stormwater inlet in layers, using a jumping compactor or other suitable equipment.

Note: The east site deceleration GAB was placed last week and tested for density by Mr. Clyde Smith.  Also, the proof-roll was performed earlier, with the county and construction contractor in attendance, for the west deceleration lane.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

 

The deceleration Lane proof roll week point

GAB work on declaration line west

proof role by county on the exiting entrance road

Storm water week backfill

The deceleration Lane proof roll week point

proof role by county on the exiting entrance road

Compacted GAB 8 inches compacted at deceleration line west

Compaction test performed on GAB east

GAB work on declaration line west

GAB work on declaration line west

GAB work on declaration line west

Technician Signature / DateSafiullah Momand, July 15, 2025
Reviewer Name / DateKenneth Mosman, July 17, 2025