Daily Field Report

Date :07/16/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :07/16/2025 09:00
Onsite Hours :06:30
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :Mostly Cloudy
Departure Time :07/16/2025 15:30
ASEC Technician Name :Safiullah Momand

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Ongoing Activities:

  1. Preparation of the entrance road (right side of Shalley Boulevard) for subgrade proof-rolling.

  2. Placement of Graded Aggregate Base (GAB) on the left side of the entrance road (left side of Shalley Boulevard).

  3. Curb removal at the deceleration lane on the west side of the project – Nature Walk, 7 Hills Amenities.

Observations and Recommendations by ASEC:

Subgrade proof-rolling for the entrance road (right side of Shalley Boulevard) was conducted at 1:00 PM in the presence of representatives from Paulding County (Mr. Mike Keener), the site contractor, and our ASEC representative. Based on the proof-roll evaluation, ASEC provided the following recommendations:

  • Portion 1: Undercut an area measuring 53 ft x 15 ft to a minimum depth of 4 inches and place GAB in the undercut area.

  • Portion 2: Undercut an area measuring 197 ft x 12 ft to a minimum depth of 4 inches and place GAB in the undercut area.

  • Portion 3: Undercut an area measuring 77 ft x 12 ft to a minimum depth of 4 inches and place GAB in the undercut area.

  • Portion 4: Undercut an area measuring 23 ft x 8 ft to a minimum depth of 4 inches and place GAB in the undercut area.

(All areas are marked and documented in the attached site photographs.)

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Subgrade prepared for Proof role purpose

Subgrade prepared for Proof role purpose

Subgrade prepared for Proof role purpose

Proof Rolling with county, contractor and ASEC

Proof Rolling with county, contractor and ASEC

Marked places after proof rolling

Marked places after proof rolling

GAB work ongoing

Curb removal work at the deceleration Lane West

GAB work

Curb removal work at the deceleration Lane West

Technician Signature / DateSafiullah Momand, July 16, 2025
Reviewer Name / DateKenneth Mosman, July 17, 2025