Daily Field Report

Date :07/22/2025
Project No :2024C213
Client Company :WDG
Arrival Time :07/22/2025 06:30
Onsite Hours :00:30
Name of the Project :Covington Town Center PH II
Project Location :Covington, GA
Weather :sunny
Departure Time :07/22/2025 07:00
ASEC Technician Name :Sean Willett

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Our ASEC representative was on site as requested by the contractor (Fulcrum) to observe the placement of GAB (Graded Aggregate Base) in the roadways.

A GAB sample was taken and returned to our lab to perform a moisture-density relationship (proctor). Our representative also noticed the placement of concrete curbing.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

sample taken from this pile

Technician Signature / DateSean Willett, July 22, 2025
Reviewer Name / DateKenneth Mosman, August 04, 2025