Skip to content

Daily Field Report

Date :07/16/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :07/16/2025 9:30
Onsite Hours :03:30
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :sunny
Departure Time :07/16/2025 13:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, a representative from AS Engineering and Consulting (ASEC) visited the site to perform quality control inspection and testing services. Visual observation techniques were used to verify compliance with the project drawings, specifications, applicable codes, and approved material submittals.

During the site visit, the contractor mortared the pipes into the drainage box and tied in the gutter downspouts to the box. Hydroseeding was also performed using a mix of lovegrass, clover, and fescue. Additionally, hand compactors were used to compact the soil around the house.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, July 16, 2025
Reviewer Name / DateKenneth Mosman, August 08, 2025