Skip to content

Concrete Test Report

Date :07/30/2025
Project No :2023C159
Client Company :CW Matthews
Arrival Time : 11:45
Onsite Hours :
Name of the Project :Airfield Repairs 2021-23
Project Location :HJAIA, Atlanta, GA
Weather :
Departure Time :
ASEC Technician Name :

Concrete Placement Information

Location(S): N/A
Testing: 1 Set of concrete specimens (5 per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The specimen will remain on site for the initial 24-48 hrs curing.
Compliance:

Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)

Deviations and/or noncompliances were noted during the field placement (refer to remarks below)

Specimen
Pick Up:
1 Sets of concrete specimens/ 5 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing: Specimen were stored for the initial 24 hours.
Near the poured structure
In an insulated curing box
Other
Remarks: First 6 cubic yards of concrete was placed in the first apron. The second 6 cubic yards were placed on the second Apron for a total of 12 cubic yards. Tests were taken on a sample from the first truck. The tests and results were: Concrete temp = 94°F Slump = 1.5" Air = 3.7% Unit weight = 144.1 pcf One (1) set of five (5) cylinders were cast.
Technician Signature / DateSolomon Cherie, July 30, 2025