Daily Field Report

Date :08/01/2025
Project No :2023C195
Client Company :Toll Bros. Inc.
Arrival Time :08/01/2025 11:30
Onsite Hours :05:15
Name of the Project :Kimbal Bridge Tract
Project Location :Alpharetta
Weather :
Departure Time :08/01/2025 16:45
ASEC Technician Name :Solomon Cherie

Observations/Finding

  • I and Bal went to the project site to do DCP. We figure out it was 4 lots that is going to have dcp tests.
  • I did the dcp tests for Lot#10 and Lot#11.
  • The dcp tests were done manually at four corners for each Lots.
  • Two tests were encountered rock and an offset of 2′ far were done,
  • The remaining tests were done to 4 feet.
  • All of them were showing 8 and above blows of dcp
  • The result finally was analuazed and  synthesized and presumed to pass the test.
Technician Signature / DateSolomon Cherie, August 1, 2025
Reviewer Name / DateKenneth Mosman, August 05, 2025