Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Our ASEC representative along with Clyde Smith of ASEC made recommendations for the amount of cut to be taken out of the curbline and backfill with GAB. For the section between Azalea Crossing Lot #317 and #331 as well as the next closest lot going down in address on the same side of the road.