Density Test Report
Date :08/27/2025
Project No :2025C146
Client Company :Davidson Homes, LLC
Arrival Time :08/27/2025 10:15
Onsite Hours :
Name of the Project :Greene Farms Subdivision
Project Location :1451 Highway 113, Cartersville, Georgia
Weather :
Departure Time :
ASEC Technician Name :Solomon Cherie
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 08/27/2025 | 1 | 19.4 | 94.7 | ASECP002 | 99.4 | 22.4 | 95.3 | 95 | D2937 | Pass |
| Location : | Storm line between MH C3 & C4, Elv/Depth :at finished grade | |||||||||
| Comment : | ||||||||||
| 08/27/2025 | 2 | 14.6 | 101.6 | ASECP005 | 106.8 | 16.5 | 95.1 | 95 | D2937 | Pass |
| Location : | Lot #71, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | ||||||||||
| 08/27/2025 | 3 | 13.4 | 97.3 | ASECP005 | 106.8 | 16.5 | 91.1 | 95 | D2937 | Fail |
| Location : | Lot #68, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | This area should be recompacted and restested. | |||||||||
Technician Signature / DateSolomon Cherie, August 27, 2025
Reviewer Name / DateKenneth Mosman, September 17, 2025