Daily Field Report

Date :09/10/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :09/10/2025 12:30
Onsite Hours :03:30
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :Sunny
Departure Time :09/10/2025 16:00
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was on site to observe proof-rolling 0f subgrade soils at the entrance and exit drives off Seven Hills Boulevard. The contractor continued subgrade preparation. The writer stood by for completion of grading to observe proof-rolling, however, the contractor cancelled this activity until tomorrow.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Sub grade prep. at exit drive

Technician Signature / DateClyde Smith, September 10, 2025
Reviewer Name / DateKenneth Mosman, October 14, 2025