Density Test Report

Date :09/02/2025
Project No :2025C215
Client Company :Artisan
Arrival Time :09/02/2025 09:30
Onsite Hours :9:00
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :09/02/2025 18:30
ASEC Technician Name :Safiullah Momand

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/02/2025 1 16.1 96.3 2025-031 SP 101.0 20.7 95.3 95 D2937 Pass
Location : 45 ft north side of 5A manhole, Elv/Depth :4 feet below finished grade
Comment :
09/02/2025 2 17.6 102.0 2025-031 SP 101.0 20.7 101.0 95 D2937 Pass
Location : 22 ft south from 5A, Elv/Depth :8 feet below finished grade
Comment :
09/02/2025 3 13.2 90.8 2025-032 SP 94.9 25.0 95.7 95 D6938 Pass
Location : Lot #10, Elv/Depth :6 feet from finished grade
Comment : Gauge Serial No. :3430
09/02/2025 4 12.3 93.4 2025-031 SP 101.0 20.7 92.5 95 D6938 Fail
Location : Lot #12, Elv/Depth :2 feet from finished grade
Comment : Recompation required. Gauge Serial No. :3430
09/02/2025 5 7.4 110.1 2025-033 SP 104.0 16.2 105.9 95 D6938 Pass
Location : Lot #11, Elv/Depth :5 feet from finished grade
Comment : Gauge Serial No. :3430
Technician Signature / DateSafiullah Momand, September 2, 2025
Reviewer Name / DateKenneth Mosman, September 17, 2025