Density Test Report

Date :08/29/2025
Project No :2025C215
Client Company :Artisan
Arrival Time :08/29/2025 10:00
Onsite Hours :05:30
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :08/29/2025 15:30
ASEC Technician Name :Safiullah Momand

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
08/29/2025 1 18.3 89.0 2025-031 SP 101.0 20.7 88.1 98 D6938 Fail
Location : 45ft west of Manhole 6, Elv/Depth :at finished grade
Comment : Recompaction required Gauge Serial No. :3440
08/29/2025 2 16.7 89.3 2025-031 SP 101.0 20.7 88.4 98 D6938 Fail
Location : 120 ft west of Manhole 6, Elv/Depth :at finished grade
Comment : Recompaction required Gauge Serial No. :3440
08/29/2025 3 21.7 96.4 2025-031 SP 101.0 20.7 95.4 98 D6938 Fail
Location : 300 ft west side of Manhole 6A, Elv/Depth :at finished grade
Comment : Recompaction required Gauge Serial No. :3440
Technician Signature / DateSafiullah Momand, August 29, 2025
Reviewer Name / DateKenneth Mosman, September 17, 2025