Density Test Report

Date :09/15/2025
Project No :2025C224
Client Company :C. W. MATTHEWS CONTRACTING CO., INC.
Arrival Time :09/15/2025 07:45
Onsite Hours :11:45
Name of the Project :PDK Airport - RUNWAY 3R-21L KEEL REPLACEMENT
Project Location :PDK AIRPORT, DEKALB County, GA
Weather :sunny
Departure Time :09/15/2025 19:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/15/2025 1 8.7 133.1 2025-037-MP 132.9 8.2 100.2 100 D6938 Pass
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 2 8.7 123.4 2025-037-MP 132.9 8.2 92.9 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 3 9.1 122.9 2025-037-MP 132.9 8.2 92.5 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 4 8.2 122.8 2025-037-MP 132.9 8.2 92.4 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 5 8.2 124.6 2025-037-MP 132.9 8.2 93.8 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 6 8.1 124.6 2025-037-MP 132.9 8.2 93.8 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 7 8.1 124.6 2025-037-MP 132.9 8.2 93.8 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 8 8.0 124.5 2025-037-MP 132.9 8.2 93.7 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
09/15/2025 9 8.2 122.8 2025-037-MP 132.9 8.2 92.4 100 D6938 Fail
Location : Phase 1B, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
Technician Signature / DateAminullah Azimi, September 15, 2025
Reviewer Name / DateKenneth Mosman, October 10, 2025