Daily Field Report

Date :10/06/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :10/06/2025 08:00
Onsite Hours :02:30
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :cloudy
Departure Time :10/06/2025 10:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative visited the above site to observe proof-rolling of the subbase stone at the drive entrance and exit lanes. The proof-roll was observed by using a loaded tandem dump truck making two passes over all areas. The writer along with a member from NWGP and Paulding County observed the proof-roll. No severe pumping/rutting was observed under truck traffic.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

 

Technician Signature / DateClyde Smith, October 6, 2025
Reviewer Name / DateKenneth Mosman, October 15, 2025