Daily Field Report

Date :10/08/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :10/08/2025 13:30
Onsite Hours :03:30
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :Sunny
Departure Time :10/08/2025 17:00
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our ASEC representative was on site with Paulding County officials observing previous placed asphalt base material at the drive exit for Seven Hills Amenities. The in-place base asphalt paving did not appear to match existing concrete curb grades. Paulding County requested depth checks of the in-place base mix at several locations along curb line by saw cutting. Saw cuts were performed at three locations with the following results:

#1.         4.25″

#2          3.75″

#3.         4.5″

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Depth 4.5"

Depth 3.75"

Depth 3.75"

Curve line marked by county

Depth 4.25"

Technician Signature / DateClyde Smith, October 8, 2025
Reviewer Name / DateKenneth Mosman, October 09, 2025