Density Test Report

Date :10/22/2025
Project No :2025C260
Client Company :Artisan
Arrival Time :10/22/2025 11:
Onsite Hours :06:00
Name of the Project :NW (PHASE 2) Parkway Extension
Project Location :Dallas
Weather :sunny
Departure Time :10/22/2025 17:00
ASEC Technician Name :Mahendra Mylabathula

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
10/22/2025 1 19.2 97.5 2025-032 SP 94.9 25.0 102.7 95 D6938 Pass
Location : Detention pond, Elv/Depth :1 foot below finished grade
Comment : Gauge Serial No. :3430
10/22/2025 2 16.8 95.5 2025-032 SP 94.9 25.0 100.6 95 D6938 Pass
Location : detention pond, Elv/Depth :2 feet below finished grade
Comment : Gauge Serial No. :3430
Technician Signature / DateMahendra Mylabathula, October 22, 2025
Reviewer Name / DateKenneth Mosman, November 07, 2025