Density Test Report
Date :10/22/2025
Project No :2025C260
Client Company :Artisan
Arrival Time :10/22/2025 11:
Onsite Hours :06:00
Name of the Project :NW (PHASE 2) Parkway Extension
Project Location :Dallas
Weather :sunny
Departure Time :10/22/2025 17:00
ASEC Technician Name :Mahendra Mylabathula
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 10/22/2025 | 1 | 19.2 | 97.5 | 2025-032 SP | 94.9 | 25.0 | 102.7 | 95 | D6938 | Pass |
| Location : | Detention pond, Elv/Depth :1 foot below finished grade | |||||||||
| Comment : | Gauge Serial No. :3430 | |||||||||
| 10/22/2025 | 2 | 16.8 | 95.5 | 2025-032 SP | 94.9 | 25.0 | 100.6 | 95 | D6938 | Pass |
| Location : | detention pond, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | Gauge Serial No. :3430 | |||||||||
Technician Signature / DateMahendra Mylabathula, October 22, 2025
Reviewer Name / DateKenneth Mosman, November 07, 2025