Daily Field Report

Date :11/14/2025
Project No :2025C260
Client Company :Artisan
Arrival Time :11/14/2025 15:00
Onsite Hours :01:00
Name of the Project :NW (PHASE 2) Parkway Extension
Project Location :Dallas
Weather :Sunny
Departure Time :11/14/2025 16:00
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date the writer made a site visit to observe placement of embankment slope fill using stripped topsoil from parkway mixed with structure fill at elevations 845, 836 and 829. The fill placement was suitable as per job plans and specifications. The fill was spread with a dozer and compacted with a 815 sheep-foot roller.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Fill placement at slope embankment ,topsoil and structural fill .

Technician Signature / DateClyde Smith, November 14, 2025
Reviewer Name / DateKenneth Mosman, November 25, 2025