Skip to content

Daily Field Report

Date :11/15/2025
Project No :2025C244
Client Company :McCallan Group
Arrival Time :11/15/2025 08:00
Onsite Hours :07:00
Name of the Project :Cassville Rd tract, proposed Burrito Wrap
Project Location :Cartersville
Weather :sunny
Departure Time :11/15/2025 15:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

The crew began work at location SD3-B for the pond, where they cleared the site, including the removal of trees, roots, and debris, and stockpiled the cleared materials in a designated area for disposal.

A proof-roll was performed between Buildings #15 through #19.  No visible severe movement, rutting, or pumping was observed during testing.

In addition, test pits were excavated as per the plan at locations X6 through X13 to verify existing soil conditions and utility alignments.  A separate report of test pit results will be submitted at a later date.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you

Technician Signature / DateSamara Simha Reddy Kandi, November 15, 2025
Reviewer Name / DateKenneth Mosman, November 24, 2025