Daily Field Report

Date :11/19/2025
Project No :2025C244
Client Company :McCallan Group
Arrival Time :11/19/2025 07:30
Onsite Hours :11:00
Name of the Project :Cassville Rd tract, proposed Burrito Wrap
Project Location :Cartersville
Weather :sunny
Departure Time :11/19/2025 18:30
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Work started at both RCP locations, where the crew removed the formwork, backfilled the soil, and compacted the area using a jumping jack compactor.

The crew then cleared the site between Buildings #45 and #47 and compacted the SD3-B pond trench slopes on both the inside and outside.

At the SD3-A pond, two pond drainage access structures were constructed to facilitate stormwater flow. In addition, a crew from the erosion control company sprayed green hydroseed mixture on the inside and outside slopes of the SD3-A pond trench using a hydroseeder truck, and straw erosion control blankets were installed along one side of the trench to stabilize the slope.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateSamara Simha Reddy Kandi, November 19, 2025
Reviewer Name / DateKenneth Mosman, November 24, 2025