- Density Test Report Report ID: 88732
- Edit Download Report
Density Test Report
Date :12/11/2025
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :12/11/2025 11:00
Onsite Hours :05:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :sunny
Departure Time :12/11/2025 16:00
ASEC Technician Name :Samara Simha Reddy Kandi
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 12/11/2025 | 1 | 24.2 | 88.6 | 2025-057 | 92.1 | 25.7 | 96.2 | 95 | D2937 | Pass |
| Location : | Pond 3, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | ||||||||||
| 12/11/2025 | 2 | 23.2 | 88.1 | 2025-057 | 92.1 | 25.7 | 95.7 | 95 | D2937 | Pass |
| Location : | Pond 3, Elv/Depth :4 feet below finished grade | |||||||||
| Comment : | ||||||||||
| 12/11/2025 | 3 | 23.7 | 87.1 | 2025-059 | 88.7 | 22.0 | 98.2 | 95 | D2937 | Pass |
| Location : | Pond 1, Elv/Depth :2 feet below finished grade | |||||||||
| Comment : | ||||||||||
Technician Signature / DateSamara Simha Reddy Kandi, December 11, 2025
Reviewer Name / DateKenneth Mosman, January 30, 2026