Skip to content

Density Test Report

Date :12/15/2025
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :12/15/2025 07:45
Onsite Hours :9:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :sunny
Departure Time :12/15/2025 16:45
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
12/15/2025 1 24.5 88.4 2025-057 92.1 25.7 96.0 95 D2937 Pass
Location : Pond 1, Elv/Depth :2 feet below finished grade
Comment :
12/15/2025 2 23.9 88.5 2025-057 92.1 25.7 96.1 95 D2937 Pass
Location : Pond 1, Elv/Depth :4 feet below finished grade
Comment :
Technician Signature / DateSamara Simha Reddy Kandi, December 15, 2025
Reviewer Name / DateKenneth Mosman, January 30, 2026