Density Test Report

Date :12/22/2025
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :12/22/2025 08:45
Onsite Hours :08:45
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :sunny
Departure Time :12/22/2025 17:30
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
12/22/2025 1 24.8 88.1 2025-057 92.1 25.7 95.7 95 D2937 Pass
Location : Pond 1 N 1413759.64 E 2305679.53 , Elv/Depth :1.5 feet below finished grade
Comment :
12/22/2025 2 21.1 90.2 2025-059 88.7 22.0 101.7 95 D2937 Pass
Location : Pond 1 N 1413785.30 E 2305607.67, Elv/Depth :1.5 feet below finished grade
Comment :
Technician Signature / DateSamara Simha Reddy Kandi, December 22, 2025
Reviewer Name / DateKenneth Mosman, February 02, 2026