- Density Test Report Report ID: 88812
- Edit Download Report
Density Test Report
Date :12/23/2025
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :12/23/2025 08:00
Onsite Hours :9:30
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :sunny
Departure Time :12/23/2025 17:30
ASEC Technician Name :Samara Simha Reddy Kandi
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 12/23/2025 | 1 | 25.2 | 82.3 | 2025-057 | 92.1 | 25.7 | 89.4 | 95 | D2937 | Fail |
| Location : | Building #15, Elv/Depth :1 foot below finished grade | |||||||||
| Comment : | Top soil concentration mixed in with structural fill. | |||||||||
| 12/23/2025 | 2 | 26.3 | 85.1 | 2025-059 | 88.7 | 22.0 | 95.9 | 95 | D2937 | Pass |
| Location : | Building #15, Elv/Depth :1 foot below finished grade | |||||||||
| Comment : | After removing top soil and replacement/recompaction. | |||||||||
Technician Signature / DateSamara Simha Reddy Kandi, December 23, 2025
Reviewer Name / DateKenneth Mosman, January 30, 2026