Density Test Report

Date :12/24/2025
Project No :2025C216
Client Company :Artisan
Arrival Time :12/24/2025 07:00
Onsite Hours :05:00
Name of the Project :NW (Lots) Unit 4 PH 1A & 1B
Project Location :Dallas
Weather :Sunny
Departure Time :12/24/2025 12:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
12/24/2025 1 15.0 110.3 2025-035 SP 107.8 13.0 102.3 95 D6938 Pass
Location : Pipeline 11 to 12, Elv/Depth :2 to 3 feet below finished grade
Comment : blasted rock present Gauge Serial No. :77-19952
12/24/2025 2 15.2 109.1 2025-035 SP 107.8 13.0 101.2 95 D6938 Pass
Location : Pipeline 11 to 12, Elv/Depth :2 to 3 feet below finished grade
Comment : Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, December 24, 2025
Reviewer Name / DateKenneth Mosman, February 02, 2026