Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
On the above date our representative was on site to observe the grading contractor continue to place fill for the cul de sac basement lots in compacted lifts. The writer performed density tests during fill placement using a Troxler Nuclear gauge model 3430, serial no. 91643. Compaction results were in compliance with job specifications. The contractor also spread mulch chips for the north side toe of slope embankment.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Fill placement and density tests at basement lots


Grassing and mat blanketing